This report covers design and construction of 30 in. (760 mm) diameter or larger foundation piers constructed by excavation of a hole in a subgrade that is later filled with concrete. The 30 in.(760 mm) diameter boundary is an arbitrary size; smaller-diameter drilled piers can be designed and installed in accordance with ACI 543R. Although determination of overall pier size and concrete section design are two basic drilled pier design procedures, emphasis is focused on the determination of overall pier size, which is affected by the interaction between subgrade and pier. Because pier capacity is significantly affected by construction means and methods, the licensed design professional should understand these limitations. Construction methods described include excavation, casing, reinforcing steel installation, and concrete placement.Acceptance criteria and recommended procedures for construction, engineering, and evaluation are presented. Keywords: bearing capacity; caisson; casing; excavation; foundation; geotechnical engineering; lateral pressure; lining; slurry; tremie.
PDF Catalog
PDF Pages | PDF Title |
---|---|
3 | CONTENTS |
4 | CHAPTER 1— INTRODUCTION AND SCOPE 1.1—Introduction 1.2—Scope CHAPTER 2— NOTATION AND DEFINITIONS 2.1—Notation 2.2—Definitions |
5 | CHAPTER 3— GENERAL CONSIDERATIONS 3.1—General 3.2—The structural and geotechnical teams |
6 | 3.3—Factors to consider 3.4—Pier types |
7 | 3.5—Geotechnical considerations |
9 | CHAPTER 4— DESIGN 4.1—Loads |
10 | 4.2—Loading conditions |
11 | 4.3—Vertically loaded piers 4.4—Laterally loaded piers |
17 | 4.5—Piers socketed in rock |
18 | 4.6—Strength design of piers 4.7—Pier configuration |
19 | CHAPTER 5— CONSTRUCTION MEANS AND METHODS 5.1—Excavation and casing |
20 | 5.2—Placing reinforcement 5.3—Dewatering, concreting, and removal of casing |
21 | 5.4—Slurry displacement method |
23 | 5.5—Safety |
24 | CHAPTER 6— CONSTRUCTION ENGINEERING AND TESTING 6.1—Scope 6.2—Geotechnical field representative 6.3—Preconstruction activities |
25 | 6.4—Construction geotechnical engineering procedures |
27 | 6.5—Concrete placement |
29 | 6.6—Post-construction assessment 6.7—Reports 6.8—Criteria for acceptance |
30 | 6.9—Corrective measures CHAPTER 7— REFERENCES Authored documents |