Shopping Cart

No products in the cart.

ASME PTC 47.1 2017 R2022

$98.04

ASME PTC 47.1 – 2017(R2022) – Cryogenic Air Separation Unit of an Integrated Gasification Combined Cycle Power Plant

Published By Publication Date Number of Pages
ASME 2017 91
Guaranteed Safe Checkout
Category:

If you have any questions, feel free to reach out to our online customer service team by clicking on the bottom right corner. We’re here to assist you 24/7.
Email:[email protected]

This Code applies to ASUs of any size, in either a single-train or multitrain configuration. It can be used to measure the performance of an ASU in its normal operating condition, with all equipment in a new, clean, and fully functional condition. This Code provides methods and procedures explicitly for ASUs employing electric-motor-drive compression equipment, with or without the use of steam and/or electric power for internal regenerative processes. There is no intent to restrict the use of this Code for non-motor-driven compression equipment, nor for ASUs that use other heat inputs for internal regenerative processes, provided the explicit test procedures can be met. (a) Test Conditions. To test a particular ASU, the following conditions shall be met: A means shall be available to determine, through either direct or indirect measurements, all of the electric power inputs entering the test boundary, as well as any electric power outputs leaving the test boundary. A means shall be available to determine, through either direct or indirect measurements, the purity and conditions of all of the pressurized flows entering or leaving the test boundary. A means shall be available to determine, through either direct or indirect measurements, all of the parameters to correct the results from the test to a base reference condition. The test uncertainties shall be less than or equal to the uncertainty limits. (b) Tests Outside the Scope of ASME PTC 47.1. Tests addressing performance-related issues other than those specified in para. (a) above are outside the scope of this Code. These include, but are not limited to, the following: emissions tests operational demonstration tests pertaining to non-steady-state or off-design conditions liquid production tests conducted to determine the capability of producing liquefied products from the ASU at rates other than the specified design flows reliability tests conducted over extended periods of time beyond the required testing period ASME PTC 47.1 is part of a series comprised of five PTCs that describe testing procedures for an integrated gasification combined cycle (IGCC) power plant: PTC 47-2006 PTC on Integrated Gasification Combined Cycle Plants PTC 47.1-2017 – Cryogenic Air Separation Unit of an IGCC Power Plant PTC 47.2-2019 – Gasification Block of an IGCC Power Plant PTC 47.3 (to be released) – Syngas Conditioning Block of an IGCC Power Plant PTC 47.4-2015 – Power Block of an IGCC Power Plant

PDF Catalog

PDF Pages PDF Title
4 CONTENTS
7 NOTICE
8 FOREWORD
9 ASME PTC Committee Roster
10 CORRESPONDENCE WITH THE PTC COMMITTEE
12 INTRODUCTION
14 Section 1 Object and Scope
1-1 OBJECT
1-1.1 Accuracy
1-1.2 Performance Characteristics
1-2 SCOPE
15 1-3 TEST UNCERTAINTY
1-4 REFERENCES
Table 1-3-1 Largest Expected Test Uncertainty
16 Section 2 Definitions and Description of Terms
2-1 INTRODUCTION
2-2 AIR SEPARATION UNIT EQUIPMENT DEFINITIONS
17 2-3 GENERAL DEFINITIONS
18 2-4 SYMBOLS
2-5 ABBREVIATIONS USED IN SUBSCRIPTS
19 Section 3 Guiding Principles
3-1 INTRODUCTION
3-2 TEST BOUNDARY AND REQUIRED MEASUREMENTS
3-2.1 Test Boundary Definition
3-2.2 Required Measurements
20 Figure 3-2.1-1 Generic ASU Test Boundary
Figure 3-2.1-2 Nonintegrated ASU Test Boundary
21 3-2.3 Pretest Uncertainty Analysis
3-3 TEST PLAN
3-3.1 Schedule of Test Activities
3-3.2 Responsibilities of Parties to the Test
Figures
Figure 3-2.1-3 Integrated ASU Test Boundary
22 3-3.3 Test Procedures
3-4 TEST PREPARATIONS
23 3-4.1 Requirements for Agreements
24 3-4.2 Test Apparatus
3-4.3 Test Personnel
3-4.4 Equipment Inspection and Cleanliness
3-4.5 Preliminary Testing
25 3-5 CONDUCT OF THE TEST
3-5.1 Methods of Operation Prior to and During Tests
26 3-5.2 Starting and Stopping Tests and Test Runs
3-5.3 Adjustments Prior to and During Tests
27 3-5.4 Duration, Number, and Evaluation of Test Runs
28 3-5.5 Constancy of Test Conditions
3-6 CALCULATION AND REPORTING OF RESULTS
3-6.1 Data Reduction
3-6.2 Rejection of Readings
3-6.3 Inconsistent Measurements
3-6.4 Invalid Test Runs
Figure 3-5.4.3-1 Uncertainty Intervals
29 3-6.5 Test Records
3-6.6 Test Report
30 Section 4 Instruments and Methods of Measurement
4-1 GENERAL REQUIREMENTS
4-1.1 Introduction
4-1.2 Measurements
31 4-1.3 Instrumentation
4-1.4 Instrument Calibration
34 4-1.5 Instrument Verification
4-2 PRESSURE MEASUREMENT
4-2.1 Introduction
35 4-2.2 Required Uncertainty
4-2.3 Recommended Pressure Measurement Devices
36 4-2.4 Absolute Pressure Measurements
37 4-2.5 Gauge Pressure Measurements
4-2.6 Differential Pressure Measurements
38 Figure 4-2.6.2-1 Five-Way Manifold
39 4-3 TEMPERATURE MEASUREMENT
4-3.1 Introduction
4-3.2 Required Uncertainty
Figure 4-2.6.2-2 Water Leg Correction for Flow Measurement
40 4-3.3 Recommended Temperature Measurement Devices
41 Figure 4-3.3.2.1-1 Three- and Four-Wire RTDs
42 4-3.4 Calibration of Primary Parameter Temperature Measurement Devices
4-3.5 Temperature Scale
43 4-3.6 Typical Applications
Figure 4-3.6.2-1 Flow-Through Well
44 4-4 HUMIDITY MEASUREMENT
4-4.1 Introduction
4-4.2 Required Uncertainty
45 Figure 4-3.6.3-1 Duct Measurement Points
46 4-4.3 Recommended Humidity Measurement Devices
47 4-5 FLOW MEASUREMENT
4-5.1 Introduction
4-5.2 Water and Steam
48 4-5.3 Gas Flow Measurements
4-6 GAS PURITY MEASUREMENTS
4-6.1 Introduction
49 4-6.2 Required Uncertainty
4-6.3 Gas Purity Measurement Devices
4-7 SPEED MEASUREMENTS
4-8 ELECTRICAL MEASUREMENTS
4-8.1 Introduction
4-8.2 Polyphase AC Electrical Measurement System Connections
50 4-8.3 Electrical Metering Equipment
Figure 4-8.2-1 Three-Wire Metering Systems
51 4-8.4 Instrument Transformers
4-8.5 Calculation of Corrected Average Power or Corrected Total Energy
4-8.6 Measurement of Auxiliary Electrical Load
52 4-8.7 Measurement of Step-Up and Step-Down Transformers
4-9 DATA COLLECTION AND HANDLING
4-9.1 Introduction
4-9.2 Data Management
4-9.3 Data Acquisition System Selection
53 4-10 LOSSES
4-10.1 Gearbox Losses
4-10.2 Fixed Losses
4-10.3 Variable Losses
54 Section 5 Calculations and Results
5-1 FUNDAMENTAL EQUATIONS
Tables
Table 5-1-1 Summary of Additive and Multiplicative Correction Factors in Fundamental Performance Equations
55 5-2 POWER TERMS IN THE FUNDAMENTAL EQUATIONS
5-3 DISCUSSION OF APPLICATION OF CORRECTION FACTORS
5-3.1 Dry Flow Factors, MDFRA,j and MDFRC,j
5-3.2 Moisture Content Factors, MMCMO2, MMCLPO2, MMCA,j, and MMCC,j
56 Figure 5-2-1 Typical Nonintegrated ASU Test Boundary
57 Figure 5-2-2 Typical Integrated ASU Test Boundary
58 5-3.3 Suction Temperature Factors, MSTMO2, MSTLPO2, MSTA,j, and MSTC,j
5-3.4 Suction Pressure Factors, MSPMO2, MSPLPO2, MSPA,j, and MSPC,j
5-3.5 Discharge Pressure Factors, MDPA,j and MDPC,j
5-3.6 Cooling Water Factors, MCWITA,j and MCWITC,j
5-4 MODEL FUNCTIONAL REQUIREMENTS
5-4.1 Completeness
5-4.2 Flexibility
5-4.3 Accuracy
59 5-4.4 Model Validation
5-5 DEGRADATION
60 Section 6 Report of Results
6-1 GENERAL REQUIREMENTS
6-2 EXECUTIVE SUMMARY
61 6-3 INTRODUCTION
6-4 CALCULATIONS AND RESULTS
6-5 INSTRUMENTATION
6-6 CONCLUSIONS
6-7 APPENDICES
63 Section 7 Uncertainty Analysis
7-1 INTRODUCTION
7-1.1 Pretest Uncertainty Analysis
7-1.2 Post-Test Uncertainty Analysis
7-2 OBJECTIVE OF UNCERTAINTY ANALYSIS
7-3 DETERMINATION OF OVERALL UNCERTAINTY
64 7-4 SOURCES OF ERROR
7-5 CALCULATION OF UNCERTAINTY
Table 7-5-1 Format of Uncertainty Calculations
65 7-6 SENSITIVITY COEFFICIENTS
Table 7-5-2 Measured Parameters Needed for Uncertainty Calculations
66 7-7 SYSTEMATIC UNCERTAINTY
7-8 RANDOM STANDARD UNCERTAINTY FOR SPATIALLY UNIFORM PARAMETERS
68 7-9 RANDOM STANDARD UNCERTAINTY FOR SPATIALLY NONUNIFORM PARAMETERS
7-10 CORRELATED SYSTEMATIC STANDARD UNCERTAINTY
69 NONMANDATORY APPENDIX A SAMPLE CALCULATION
A-1 ASU DESCRIPTION AND UNIT DISPOSITION
A-2 TEST BOUNDARY DESCRIPTION
A-3 REFERENCE AND MEASURED CONDITIONS
70 Figure A-2-1 Example Case Flow Diagram
A-4 CORRECTED SPECIFIC POWER
71 Table A-3-1 Reference and Measured Data
72 A-5 CORRECTED ASU EFFECTIVENESS
A-6 CORRECTED OXYGEN PRODUCTION RATE
73 Table A-4.1-1 Main Air Compressor Corrections
74 Table A-4.1-2 Oxygen Compressor Corrections
75 Table A-4.1-3 Utility Nitrogen Compressor Corrections
76 Table A-4.1-4 LP Nitrogen Compressor Corrections
77 Table A-4.2-1 Corrected Specific Power
78 Figure A-6-1 Ambient Pressure Correction
Figure A-6-2 Ambient Temperature Correction
Table A-5-1 Corrected Effectiveness
79 Table A-6-1 Corrected Oxygen Production Rate
80 NONMANDATORY APPENDIX B SAMPLE UNCERTAINTY ANALYSIS
B-1 ACCURACY OF MEASUREMENT
81 Table B-2-1 Pressure Transmitter Characteristics
Table B-2-2 Temperature Transmitter Characteristics
B-2 GENERALIZED EXAMPLE
83 B-3 EXAMPLE CASE UNCERTAINTY
84 Table B-3-1 Uncertainty of Corrected ASU Power Input
85 Table B-3-2 Uncertainty of Corrected ASU Production Rate
86 Table B-3-3 Uncertainty of Corrected ASU Effectiveness
87 Table B-3-4 Uncertainty of Corrected ASU Specific Power
ASME PTC 47.1 2017 R2022
$98.04