ASME PTC 47.1 2017 R2022
$98.04
ASME PTC 47.1 – 2017(R2022) – Cryogenic Air Separation Unit of an Integrated Gasification Combined Cycle Power Plant
Published By | Publication Date | Number of Pages |
ASME | 2017 | 91 |
This Code applies to ASUs of any size, in either a single-train or multitrain configuration. It can be used to measure the performance of an ASU in its normal operating condition, with all equipment in a new, clean, and fully functional condition. This Code provides methods and procedures explicitly for ASUs employing electric-motor-drive compression equipment, with or without the use of steam and/or electric power for internal regenerative processes. There is no intent to restrict the use of this Code for non-motor-driven compression equipment, nor for ASUs that use other heat inputs for internal regenerative processes, provided the explicit test procedures can be met. (a) Test Conditions. To test a particular ASU, the following conditions shall be met: A means shall be available to determine, through either direct or indirect measurements, all of the electric power inputs entering the test boundary, as well as any electric power outputs leaving the test boundary. A means shall be available to determine, through either direct or indirect measurements, the purity and conditions of all of the pressurized flows entering or leaving the test boundary. A means shall be available to determine, through either direct or indirect measurements, all of the parameters to correct the results from the test to a base reference condition. The test uncertainties shall be less than or equal to the uncertainty limits. (b) Tests Outside the Scope of ASME PTC 47.1. Tests addressing performance-related issues other than those specified in para. (a) above are outside the scope of this Code. These include, but are not limited to, the following: emissions tests operational demonstration tests pertaining to non-steady-state or off-design conditions liquid production tests conducted to determine the capability of producing liquefied products from the ASU at rates other than the specified design flows reliability tests conducted over extended periods of time beyond the required testing period ASME PTC 47.1 is part of a series comprised of five PTCs that describe testing procedures for an integrated gasification combined cycle (IGCC) power plant: PTC 47-2006 PTC on Integrated Gasification Combined Cycle Plants PTC 47.1-2017 – Cryogenic Air Separation Unit of an IGCC Power Plant PTC 47.2-2019 – Gasification Block of an IGCC Power Plant PTC 47.3 (to be released) – Syngas Conditioning Block of an IGCC Power Plant PTC 47.4-2015 – Power Block of an IGCC Power Plant
PDF Catalog
PDF Pages | PDF Title |
---|---|
4 | CONTENTS |
7 | NOTICE |
8 | FOREWORD |
9 | ASME PTC Committee Roster |
10 | CORRESPONDENCE WITH THE PTC COMMITTEE |
12 | INTRODUCTION |
14 | Section 1 Object and Scope 1-1 OBJECT 1-1.1 Accuracy 1-1.2 Performance Characteristics 1-2 SCOPE |
15 | 1-3 TEST UNCERTAINTY 1-4 REFERENCES Table 1-3-1 Largest Expected Test Uncertainty |
16 | Section 2 Definitions and Description of Terms 2-1 INTRODUCTION 2-2 AIR SEPARATION UNIT EQUIPMENT DEFINITIONS |
17 | 2-3 GENERAL DEFINITIONS |
18 | 2-4 SYMBOLS 2-5 ABBREVIATIONS USED IN SUBSCRIPTS |
19 | Section 3 Guiding Principles 3-1 INTRODUCTION 3-2 TEST BOUNDARY AND REQUIRED MEASUREMENTS 3-2.1 Test Boundary Definition 3-2.2 Required Measurements |
20 | Figure 3-2.1-1 Generic ASU Test Boundary Figure 3-2.1-2 Nonintegrated ASU Test Boundary |
21 | 3-2.3 Pretest Uncertainty Analysis 3-3 TEST PLAN 3-3.1 Schedule of Test Activities 3-3.2 Responsibilities of Parties to the Test Figures Figure 3-2.1-3 Integrated ASU Test Boundary |
22 | 3-3.3 Test Procedures 3-4 TEST PREPARATIONS |
23 | 3-4.1 Requirements for Agreements |
24 | 3-4.2 Test Apparatus 3-4.3 Test Personnel 3-4.4 Equipment Inspection and Cleanliness 3-4.5 Preliminary Testing |
25 | 3-5 CONDUCT OF THE TEST 3-5.1 Methods of Operation Prior to and During Tests |
26 | 3-5.2 Starting and Stopping Tests and Test Runs 3-5.3 Adjustments Prior to and During Tests |
27 | 3-5.4 Duration, Number, and Evaluation of Test Runs |
28 | 3-5.5 Constancy of Test Conditions 3-6 CALCULATION AND REPORTING OF RESULTS 3-6.1 Data Reduction 3-6.2 Rejection of Readings 3-6.3 Inconsistent Measurements 3-6.4 Invalid Test Runs Figure 3-5.4.3-1 Uncertainty Intervals |
29 | 3-6.5 Test Records 3-6.6 Test Report |
30 | Section 4 Instruments and Methods of Measurement 4-1 GENERAL REQUIREMENTS 4-1.1 Introduction 4-1.2 Measurements |
31 | 4-1.3 Instrumentation 4-1.4 Instrument Calibration |
34 | 4-1.5 Instrument Verification 4-2 PRESSURE MEASUREMENT 4-2.1 Introduction |
35 | 4-2.2 Required Uncertainty 4-2.3 Recommended Pressure Measurement Devices |
36 | 4-2.4 Absolute Pressure Measurements |
37 | 4-2.5 Gauge Pressure Measurements 4-2.6 Differential Pressure Measurements |
38 | Figure 4-2.6.2-1 Five-Way Manifold |
39 | 4-3 TEMPERATURE MEASUREMENT 4-3.1 Introduction 4-3.2 Required Uncertainty Figure 4-2.6.2-2 Water Leg Correction for Flow Measurement |
40 | 4-3.3 Recommended Temperature Measurement Devices |
41 | Figure 4-3.3.2.1-1 Three- and Four-Wire RTDs |
42 | 4-3.4 Calibration of Primary Parameter Temperature Measurement Devices 4-3.5 Temperature Scale |
43 | 4-3.6 Typical Applications Figure 4-3.6.2-1 Flow-Through Well |
44 | 4-4 HUMIDITY MEASUREMENT 4-4.1 Introduction 4-4.2 Required Uncertainty |
45 | Figure 4-3.6.3-1 Duct Measurement Points |
46 | 4-4.3 Recommended Humidity Measurement Devices |
47 | 4-5 FLOW MEASUREMENT 4-5.1 Introduction 4-5.2 Water and Steam |
48 | 4-5.3 Gas Flow Measurements 4-6 GAS PURITY MEASUREMENTS 4-6.1 Introduction |
49 | 4-6.2 Required Uncertainty 4-6.3 Gas Purity Measurement Devices 4-7 SPEED MEASUREMENTS 4-8 ELECTRICAL MEASUREMENTS 4-8.1 Introduction 4-8.2 Polyphase AC Electrical Measurement System Connections |
50 | 4-8.3 Electrical Metering Equipment Figure 4-8.2-1 Three-Wire Metering Systems |
51 | 4-8.4 Instrument Transformers 4-8.5 Calculation of Corrected Average Power or Corrected Total Energy 4-8.6 Measurement of Auxiliary Electrical Load |
52 | 4-8.7 Measurement of Step-Up and Step-Down Transformers 4-9 DATA COLLECTION AND HANDLING 4-9.1 Introduction 4-9.2 Data Management 4-9.3 Data Acquisition System Selection |
53 | 4-10 LOSSES 4-10.1 Gearbox Losses 4-10.2 Fixed Losses 4-10.3 Variable Losses |
54 | Section 5 Calculations and Results 5-1 FUNDAMENTAL EQUATIONS Tables Table 5-1-1 Summary of Additive and Multiplicative Correction Factors in Fundamental Performance Equations |
55 | 5-2 POWER TERMS IN THE FUNDAMENTAL EQUATIONS 5-3 DISCUSSION OF APPLICATION OF CORRECTION FACTORS 5-3.1 Dry Flow Factors, MDFRA,j and MDFRC,j 5-3.2 Moisture Content Factors, MMCMO2, MMCLPO2, MMCA,j, and MMCC,j |
56 | Figure 5-2-1 Typical Nonintegrated ASU Test Boundary |
57 | Figure 5-2-2 Typical Integrated ASU Test Boundary |
58 | 5-3.3 Suction Temperature Factors, MSTMO2, MSTLPO2, MSTA,j, and MSTC,j 5-3.4 Suction Pressure Factors, MSPMO2, MSPLPO2, MSPA,j, and MSPC,j 5-3.5 Discharge Pressure Factors, MDPA,j and MDPC,j 5-3.6 Cooling Water Factors, MCWITA,j and MCWITC,j 5-4 MODEL FUNCTIONAL REQUIREMENTS 5-4.1 Completeness 5-4.2 Flexibility 5-4.3 Accuracy |
59 | 5-4.4 Model Validation 5-5 DEGRADATION |
60 | Section 6 Report of Results 6-1 GENERAL REQUIREMENTS 6-2 EXECUTIVE SUMMARY |
61 | 6-3 INTRODUCTION 6-4 CALCULATIONS AND RESULTS 6-5 INSTRUMENTATION 6-6 CONCLUSIONS 6-7 APPENDICES |
63 | Section 7 Uncertainty Analysis 7-1 INTRODUCTION 7-1.1 Pretest Uncertainty Analysis 7-1.2 Post-Test Uncertainty Analysis 7-2 OBJECTIVE OF UNCERTAINTY ANALYSIS 7-3 DETERMINATION OF OVERALL UNCERTAINTY |
64 | 7-4 SOURCES OF ERROR 7-5 CALCULATION OF UNCERTAINTY Table 7-5-1 Format of Uncertainty Calculations |
65 | 7-6 SENSITIVITY COEFFICIENTS Table 7-5-2 Measured Parameters Needed for Uncertainty Calculations |
66 | 7-7 SYSTEMATIC UNCERTAINTY 7-8 RANDOM STANDARD UNCERTAINTY FOR SPATIALLY UNIFORM PARAMETERS |
68 | 7-9 RANDOM STANDARD UNCERTAINTY FOR SPATIALLY NONUNIFORM PARAMETERS 7-10 CORRELATED SYSTEMATIC STANDARD UNCERTAINTY |
69 | NONMANDATORY APPENDIX A SAMPLE CALCULATION A-1 ASU DESCRIPTION AND UNIT DISPOSITION A-2 TEST BOUNDARY DESCRIPTION A-3 REFERENCE AND MEASURED CONDITIONS |
70 | Figure A-2-1 Example Case Flow Diagram A-4 CORRECTED SPECIFIC POWER |
71 | Table A-3-1 Reference and Measured Data |
72 | A-5 CORRECTED ASU EFFECTIVENESS A-6 CORRECTED OXYGEN PRODUCTION RATE |
73 | Table A-4.1-1 Main Air Compressor Corrections |
74 | Table A-4.1-2 Oxygen Compressor Corrections |
75 | Table A-4.1-3 Utility Nitrogen Compressor Corrections |
76 | Table A-4.1-4 LP Nitrogen Compressor Corrections |
77 | Table A-4.2-1 Corrected Specific Power |
78 | Figure A-6-1 Ambient Pressure Correction Figure A-6-2 Ambient Temperature Correction Table A-5-1 Corrected Effectiveness |
79 | Table A-6-1 Corrected Oxygen Production Rate |
80 | NONMANDATORY APPENDIX B SAMPLE UNCERTAINTY ANALYSIS B-1 ACCURACY OF MEASUREMENT |
81 | Table B-2-1 Pressure Transmitter Characteristics Table B-2-2 Temperature Transmitter Characteristics B-2 GENERALIZED EXAMPLE |
83 | B-3 EXAMPLE CASE UNCERTAINTY |
84 | Table B-3-1 Uncertainty of Corrected ASU Power Input |
85 | Table B-3-2 Uncertainty of Corrected ASU Production Rate |
86 | Table B-3-3 Uncertainty of Corrected ASU Effectiveness |
87 | Table B-3-4 Uncertainty of Corrected ASU Specific Power |