Shopping Cart

No products in the cart.

BS EN IEC 60545:2021

$198.66

Guidelines for commissioning and operation of hydraulic turbines, pump-turbines and storage pumps

Published By Publication Date Number of Pages
BSI 2021 52
Guaranteed Safe Checkout
Categories: ,

If you have any questions, feel free to reach out to our online customer service team by clicking on the bottom right corner. We’re here to assist you 24/7.
Email:[email protected]

The purpose of this document is to establish, in a general way, suitable procedures for commissioning and operation of hydraulic machines and associated equipment, and to indicate how such machines and equipment should be commissioned and operated. Commissioning and operation of the associated equipment are not described in detail in this document but is considered in the commissioning and operation procedure as a separate step. Machines of up to about 15 MW and reference diameters of about 3 m are generally covered by IEC 62006. It is understood that a guideline of this type will be binding only if the contracting parties have agreed upon it. The guidelines exclude matters of purely commercial interest, except those inextricably connected with the conduct of commissioning and operation. The guidelines are not concerned with waterways, gates, drainage pumps, cooling-water equipment, generators, motor-generators, electrical equipment (e.g. circuit breakers, transformers) etc., except where they cannot be separated from the hydraulic machinery and its equipment. Wherever the guidelines specify that documents, drawings or information are supplied by a supplier (or by suppliers), each individual supplier should furnish the appropriate information for its own supply only.

PDF Catalog

PDF Pages PDF Title
2 undefined
4 European foreword
Endorsement notice
5 English
CONTENTS
8 FOREWORD
10 1 Scope
2 Normative references
3 Terms and definitions
3.1 Machine and equipment
12 3.2 Tests, periods, operating modes
14 4 Information on operating conditions
4.1 General
4.2 Documents, data and instructions
16 4.3 Final stage of erection, before commissioning
5 Commissioning
5.1 General
5.1.1 Overview
17 5.1.2 Commissioning period
5.1.3 Operating conditions during commissioning
5.1.4 Measurements during commissioning
Figures
Figure 1 – Commissioning procedure
18 5.1.5 Grid and hydraulic conditions
5.1.6 Pre-conditions for commissioning
19 5.1.7 Health and safety during the commissioning
5.2 Commissioning co-ordinator and organisation
20 5.3 Pre-start tests
5.3.1 General
5.3.2 Prior to filling waterways
Figure 2 – Example of organisation chart for commissioning
21 5.3.3 Filling waterways
5.3.4 Prior to filling machine
22 5.3.5 Filling machine
23 5.3.6 Using the machine as a pump for initial filling of the penstock
5.4 Initial run
24 5.5 Test operation period
5.5.1 General
5.5.2 No-load tests
26 5.5.3 First synchronizing
5.5.4 Load rejection and load run
30 5.5.5 Additional tests for adjustable (variable) speed hydraulic machinery in combination with a double fed generator/motor-generator
31 5.5.6 Operation modes and mode changes
32 5.5.7 Control modes
5.5.8 Operation modes with particular functions
Figure 3 – Modes of operation of a reversible pump-turbine
33 5.5.9 Field tests for runaway speed
5.5.10 Other tests
5.6 End of commissioning
34 6 Operation
6.1 General
6.2 Test service period
6.2.1 General
6.2.2 Responsibilities
6.2.3 Outages and interruptions
6.2.4 Observations and records
35 6.2.5 End of test service period
6.3 Commercial service
6.3.1 Guarantee period
37 6.3.2 Post guarantee period
6.3.3 Special operating conditions
42 Annex A (informative)Description of different modes of operation of a reversible pump-turbine
A.1 General
A.2 From standstill (ready to operate) to standstill (auxiliary systems in operation) (01 and 10)
A.3 From standstill (auxiliary systems in operation) to no-load (synchronized) (12)
A.4 From no-load (synchronized) to standstill (21)
43 A.5 From no-load to turbine operation (23)
A.6 From turbine operation to no-load (synchronized) (32)
A.7 From no-load to synchronous condenser operation (turbine direction) (24)
44 A.8 From synchronous condenser operation (turbine direction) to no-load (42)
A.9 From synchronous condenser operation (turbine direction) to turbine operation (43:= 42 and 23)
A.10 From turbine operation to synchronous condenser operation (turbine direction) (34:= 32 and 24)
A.11 From standstill (auxiliary systems in operation) to synchronous condenser operation (turbine direction) 14 or (12 and 24)
A.12 From synchronous condenser operation (turbine direction) to standstill (41)
45 A.13 From standstill (auxiliary system in operation) to SCO (pump direction) (15)
A.14 From synchronous condenser operation (pump direction) to pump operation (56)
A.15 From pump operation to synchronous condenser operation (pump direction) (65)
A.16 From synchronous condenser operation (pump direction) to standstill (51)
A.17 From operation (pump direction) to standstill (61)
A.18 From standstill to pump operation (16)
46 A.19 From turbine – full load to pump operation (36)
A.20 From pump operation to turbine full load – quick change over (63)
A.21 Hydraulic short circuit
47 Annex B (informative)Tests for adjustable (variable) speed hydraulic machineryin combination with a double fed generator/motor-generator
B.1 Operating zone and test condition
B.1.1 General
B.1.2 Pumping operation
B.1.3 Generation operation
Figure B.1 – Pumping operation zone
48 B.1.4 Test conditions
B.2 Test items
B.2.1 Step response test by power setter
B.2.2 Guide vane opening vs. power characteristic measurement in pump and turbine operation
Figure B.2 – Generation operation zone
49 B.2.3 Confirmation of preventive control of the speed deviation from the defined speed range
B.2.4 Load (input/output) rejection test
50 Annex C (informative)Commissioning program
Table C.1 – Example for a commissioning procedure programme
51 Bibliography
BS EN IEC 60545:2021
$198.66